Schedules
The following illustrates single and multiple schedules per line. Examples only highlight critical fields.
Scenario 1
A line with a quantity of 6 requires at least one Schedule:
Schedule Num | Ship To Location | Quantity Unit | Quantity | Promised Delivery Date |
---|---|---|---|---|
1 |
Seattle |
Ea |
6 |
31/01/2014 13:00 |
Scenario 2
A line requiring multiple schedules with different shipping locations. The quantity of the split schedule must equal the total quantity of the line. For this example, the line quantity is 6:
Schedule Num | Ship To Location | Quantity Unit | Quantity | Promised Delivery Date |
---|---|---|---|---|
1 |
Seattle |
Ea |
4 |
31/01/2014 13:00 |
2 |
Chicago |
Ea |
2 |
31/01/2014 13:00 |